SpaceX wants to build a data center in the Arizona desert that would draw 6,000 megawatts of power at full build-out. That is nearly two-thirds of the all-time peak demand that Arizona Public Service, which serves about 1.5 million homes and businesses, hit across its entire system this summer
The Cochise County campus is the larger half of a plan SpaceX announced on Nov. 12 to spend more than $74 billion on two AI supercomputing sites: roughly $50 billion in southeastern Arizona and more than $24 billion at Starbase, Texas, Reuters reported. The company is pitching both as projects that pay for themselves, with on-site power in Texas, dry cooling in Arizona, and promises of lower bills and taxes for neighbors.
Residents, local officials, and now Arizona’s attorney general want proof first. Who covers the cost of the power plants, water, and grid upgrades behind AI, the company or the people who live next door, is quickly becoming the question that decides whether these campuses get built.
The stakes for SpaceX are large. Its AI segment produced more than half of its third-quarter revenue, ahead of rockets and Starlink and Fortune has reported on how renting out computing capacity to Anthropic and Google has become central to the company’s valuation. The political ground is shifting under the industry, too: voters sided against data center development in 37 of 38 local ballot contests with complete counts this month, asFortunereported after the midterms
In Texas, a land swap puts the project past a moratorium
The Texas campus is a gas-fired power plant and “super-compute facility” on 444.45 acres near the Port of Brownsville, The Texas Tribunereported. Brownsville de-annexed the land earlier this year at SpaceX’s request, after the company offered $220 million for city water and wastewater projects. The neighboring city of Starbase, which incorporated around SpaceX’s launch site in 2025, then annexed it.
That sequence leaves the project outside the reach of Brownsville’s 90-day data center moratorium, which took effect in early November. The city says its decision was based on the “information and circumstances presented at the time.”
Because the plant would generate its own electricity, SpaceX says the facility won’t draw from the public grid. It will still burn a lot of gas. The Texas Commission on Environmental Quality issued an air permit on Nov. 16 that allows 35 natural gas turbines producing 750 megawatts and up to 248 tons of nitrogen oxides a year, Newsweekreported, citing Politico.