LOUDOUN COUNTY, Va. (7News) —Loudoun County is requiring developers seeking approval for data centers and other large energy-use facilities to provide more information about their projects under anew Virginia law.
The county announced the changes Friday, saying applicants must provide details about how much electricity a facility will use, how close it would be to homes and schools, and its potential impact on the surrounding area.
Virginiadefines a high-energy-use facility as one expected to need at least 100 megawatts of electricity.
In Loudoun County, data centers are the most common example.
SEE ALSO |Amazon is backing out of planned data center project at former GW campus
Under the new rules, officials said developers must provide information about the facility’s power needs and any substationsthat would serve it. They must also show how close the project would be to homes and schoolsand assess possible noise impacts on homes and schools within 500 feet of the property.
Applicants must also explain how a proposed facility could affect water re
“The new requirements apply to all current and future legislative land use applications,” county officials said in their Friday release.
The county said the information could help officials decide whether projects follow local development plans and rules, including noise and zoning regulations.
Applicants can find the required forms and a checklist here.
3
NEWManassas woman groped, assaulted by man while waiting for rideshare11
NEWMan accused of beheading Quantico Iwo Jima statue in US illegally4
NEWLoudoun County adds new requirements for data center applications3
NEWFormer FBI officials accused of lying to Congress in Hunter Biden investigation